2023 100% Free PMI-ACP Daily Practice Exam With 210 Questions [Q11-Q35]

4/5 - (1 vote)

2023 100% Free PMI-ACP Daily Practice Exam With 210 Questions

PMI-ACP exam torrent PMI study guide

PMI-ACP certification is a valuable credential for professionals working in agile methodologies. It demonstrates their knowledge and expertise in agile principles, practices, tools, and techniques. PMI Agile Certified Practitioner certification exam is challenging, but with the right preparation, candidates can pass it and earn the PMI-ACP certification. PMI Agile Certified Practitioner certification provides a competitive advantage in the job market and can lead to career advancement opportunities.

 

NO.11 If we plan to work in a two-week iterations with thirteen iterations during the project and the team’s velocity will be twenty story points or ideal days per iterations, what will the size of the total project in story points be?

 
 
 
 

NO.12 The velocity chart, storyboard, burndown chart, and impediment list are often communicated using:

 
 
 
 

NO.13 An Agile team expects a velocity of 8. During sprint planning, the stories were estimated and prioritized in the following order:
Story A_4Story Points
Story B_2Story Points
Story C_3 Story Points
Story D_2Story Points
Which stories should the team include in Sprint 1, without splitting the stories?

 
 
 
 

NO.14 What do project reports show during the Sprint review meeting?

 
 
 
 

NO.15 The trend of work remaining across time in a Sprint, a release, or a product, with work remaining tracked on the vertical axis and the time periods tracked on the horizontal axis is called a
____________.

 
 
 
 

NO.16 Which of the following is NOT a characteristic of an Agile plan?

 
 
 
 

NO.17 What is the correct sequence of activities in release planning?

NO.18 A scrum master assumes a project that is essential to organizational growth. The project is expected to be in production for three years. What should the scrum master do first?

 
 
 
 

NO.19 Test-Driven Development (TDD) is a rapid cycle of:

 
 
 
 

NO.20 What is the first thing an agile development team should do when planning an iteration?

 
 
 
 

NO.21 User stories are temporary artifacts. They are considered relevant until the:

 
 
 
 

NO.22 At the end of first iteration, the team finishes User Stories A, Band 50% of C.
What is the team velocity?

 
 
 
 

NO.23 Which type of story would be used when an estimate is not available due to lack of knowledge of the technology required to implement the story?

 
 
 
 

NO.24 According to DeMarco, Fragmented knowledge workers may look busy but a lot of their business is just thrashing. The minimum cost penalty is :

 
 
 
 

NO.25 After completing the release plan, the team realizes that the project is very likely to have a negative ROI. What should the team do?

 
 
 
 

NO.26 Midway through a sprint. a scrum team member advises the team of a new requirement Dial may change the initial scope What should the team do?

 
 
 
 

NO.27 An agile project manager is planning the initial scope schedule, and cost range estimates on a new project. The team will be using Kanban to control work What metrics should the team use to measure performance?

 
 
 
 

NO.28 What is the sequence of Tuckman’s stages of team formation and development progress?

 
 
 
 

NO.29 What are three processes used to begin an Agile project?

 
 
 
 

NO.30 A high-performance Agile team:

 
 
 
 

NO.31 During Sprint Planning, the architect is constanly estimating higher than everyone else, and team members are increasing their estimates to accommodate her. This is an example of:

 
 
 
 

NO.32 The scrum master for a large project must provide an estimate of what can be delivered in six months.
What should the scrum master do?

 
 
 
 

NO.33 The scrum master for a large project must provide an estimate of what can be delivered in six months. What should the scrum master do?

 
 
 
 

NO.34 Which of the following is most appropriate to always participate in Planning Poker?

 
 
 
 

NO.35 A value stream map is a tool used to identify the:

 
 
 
 

Use Valid New PMI-ACP Test Notes & PMI-ACP Valid Exam Guide: https://www.actualpdf.com/PMI-ACP_exam-dumps.html

         

Related Links: myportal.utt.edu.tt myportal.utt.edu.tt myportal.utt.edu.tt myportal.utt.edu.tt myportal.utt.edu.tt myportal.utt.edu.tt

Leave a Reply

Your email address will not be published. Required fields are marked *

Enter the text from the image below