NEW QUESTION 137
Joan is a project management consultant and she has been hired by a firm to help them identify risk events within the project. Joan would first like to examine the project documents including the plans, assumptions lists, project files, and contracts. What key thing will help Joan to discover risks within the review of the project documents?

 
 
 
 

NEW QUESTION 138
Which of the following processes is described in the statement below? “This is the process of numerically analyzing the effect of identified risks on overall project objectives.”

 
 
 
 

NEW QUESTION 139
You are the project manager of the BJA Project for your company. Management is worried about one of the identified risks in your project. The risk event has a probability of 90 percent and a cost impact of $85,000. Management and you discuss possible solutions to address the risk. You share with them that for $75,000 you can reduce the probability of the risk event to 15 percent and the impact to $25,000. This solution will add three weeks to the project schedule. Management thinks this is a good idea and they would like you to add the time and cost additions to your project plan. What type of risk response is used?

 
 
 
 

NEW QUESTION 140
During what process should a project manager assign a risk owner?

 
 
 
 

NEW QUESTION 141
You work as a project manager for BlueWell Inc. You are working with Nancy, the COO of your company, on several risks within the project. Nancy understands that through qualitative analysis you have identified
80 risks that have a low probability and low impact as the project is currently planned. Nancy’s concern, however, is that the impact and probability of these risk events may change as conditions within the project may change. She would like to know where will you document and record these 80 risks that have low probability and low impact for future reference. What should you tell Nancy?

 
 
 
 

NEW QUESTION 142
You work as the project manager for Bluewell Inc. You are working on NGQQ Projectyou’re your company. You have completed the risk analysis processes for the risk events. You and the project team have created risk responses for most of the identified project risks. Which of the following risk response planning techniques will you use to shift the impact of a threat to a third party, together with the responses?

 
 
 
 

NEW QUESTION 143
Courtney is the project manager for her organization. She is working with the project team to complete the qualitative risk analysis for her project. During the analysis Courtney encourages the project team to begin the grouping of identified risks by common causes. What is the primary advantage to group risks by common causes during qualitative risk analysis?

 
 
 
 

NEW QUESTION 144
You are the project manager of your organization. Your organization will receive a bonus if the project finishes by December 20. Management has communicated this bonus to you and your project team and has asked you to evaluate the project to see if it is possible to realize the reward. The bonus offered to your organization is $750,000. You have examined the project and believe that you can crash the project for an additional $275,000 and reach the December 20 date. Management is thrilled with your assessment and they approve the crash fee. What risk response is this?

 
 
 
 

NEW QUESTION 145
A project’s risk manager successfully implements the risk management plan and the risk register. Furthermore, the risk analysis and the risk response planning are finalized. All results have been documented, and the project management plan and other project documents have been updated accordingly.
What should the risk manager do next?

 
 
 
 

NEW QUESTION 146
You are the project manager of QSL project for your organization. You are working with your project team and several key stakeholders to create a diagram that shows how various elements of a system interrelate and the mechanism of causation within the system. What diagramming technique are you using as a part of the risk identification process?

 
 
 
 

NEW QUESTION 147
A project is in the planning phase, and the risk manager establishes the risk management for the project.
Which success factors should be taken into account by the risk manager to establish a successful risk management process for the project?

 
 
 
 

NEW QUESTION 148
Your organization has a project that is expected to last 20 months but the customer would really like the project completed in 18 months. You have worked on similar projects in the past and
believe that you could fast track the project and reach the 18 month deadline. What increases when you fast track a project?

 
 
 
 

NEW QUESTION 149
You work as a project manager for BlueWell Inc. Management has asked you to work with the key project stakeholder to analyze the risk events you have identified in the project. They would like you to analyze the project risks with a goal of improving the project’s performance as a whole. What approach can you use to achieve the goal of improving the project’s performance through risk analysis with your project stakeholders?

 
 
 
 

NEW QUESTION 150
Your project has several risks that may cause serious financial impact should they happen. You have studied the risk events and made some potential risk responses for the risk events but management wants you to do more. They’d like for you to create some type of a chart that identified the risk probability and impact with a financial amount for each risk event. What is the likely outcome of creating this type of chart?

 
 
 
 

NEW QUESTION 151
The risk manager is currently performing the monitoring and reporting process. Which of the following is an input for schedule metrics?

 
 
 
 

NEW QUESTION 152
The Identify Risk process determines the risks that affect the project and document their characteristics. Why should the project team members be involved in the Identify Risk process?

 
 
 
 

NEW QUESTION 153

The project manager has asked for the P50 estimate for the project schedule. What is the P50 estimate?

 
 
 
 

NEW QUESTION 154
You are the project manager of the GGK project for your company. The GGK project has a budget of $1,265,100 and is currently 40 percent complete. In this project, you elected to add labor to the project to increase the likelihood of completing the project early as the project was only scheduled to be 35 percent complete at this time. This positive risk response, while keeping the project ahead of schedule, has added significant costs to the project. You have already spent $575,000 to reach this point in the project. Management would like to know what your cost performance index and the schedule performance index is for this project. What are these values?

 
 
 
 

NEW QUESTION 155
Which positive risk response best describes a teaming agreement?

 
 
 
 

NEW QUESTION 156
Your organization has a project that is expected to last 20 months but the customer would really like the project completed in 18 months. You have worked on similar projects in the past and believe that you could fast track the project and reach the 18 month deadline. What increases when you fast track a project?

 
 
 
 

NEW QUESTION 157
You are the project manager of the HJH project for your company. In your project, you have created the probability-impact risk matrix as shown in the following figure: If Risk D happens in this project, how much will be left in the contingency reserve?

 
 
 
 

PMI-RMP Dumps Updated Practice Test and 273 unique questions: https://www.actualpdf.com/PMI-RMP_exam-dumps.html

         

Related Links: myportal.utt.edu.tt myportal.utt.edu.tt myportal.utt.edu.tt myportal.utt.edu.tt myportal.utt.edu.tt www.stes.tyc.edu.tw

Leave a Reply

Your email address will not be published. Required fields are marked *

Enter the text from the image below